Free tool
MoSCoW prioritization tool with RICE and weighted scoring
- No sign-up, no email
- Nothing stored
In short
Prioritization puts a list of work in order so that the team does the most valuable things first. MoSCoW sorts items into Must, Should, Could and Won't and this tool checks that the Musts leave room in your effort budget. It also scores items with RICE or a weighted model, plots them on an impact and effort grid and sorts tasks into an Eisenhower matrix.
Rank your list
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
In the same unit as the items: days, points.
60% is the DSDM rule of thumb. Change it if your team uses another.
Items
Must: the release fails without it. Should: important but a workaround exists. Could: nice to have. Won't: agreed not to do this time.
| Item | Group | Effort | Remove |
|---|---|---|---|
- Must have (2)
- 18 · 56.25%
- Should have (1)
- 9 · 28.13%
- Could have (1)
- 5 · 15.63%
- Won't have this time (1)
- 30 not planned
- Planned effort (must, should, could)
- 32
How it is calculated
- MoSCoW effort check
- The effort of each group as a share of the planned effort (Must, Should and Could together). Must items above 60% of it raise a warning, a rule of thumb from the DSDM method that you can change.
- RICE
- Reach times impact times confidence, divided by effort. Confidence is a percentage and effort must be above zero.
- Weighted score
- The sum of weight times rating for each criterion, divided by the sum of the weights, so the score stays on your rating scale.
- Impact and effort
- High impact with low effort is a quick win, high with high is a major project, low with low is a fill-in and low impact with high effort is one to avoid.
- Eisenhower
- Urgent and important: do now. Important only: schedule. Urgent only: delegate. Neither: drop.
Worked example
- A feature with reach 1,000, impact 2, confidence 80% and effort 4 scores 1,000 × 2 × 0.8 ÷ 4 = 400.
- Ratings of 4, 2 and 5 on criteria weighted 5, 3 and 2 give (20 + 6 + 10) ÷ 10 = 3.6.
What it assumes
- The scales are the ones you choose and the page states them. Agree on what a score means before the team rates items.
- The 60% limit for Must items is a rule of thumb, not a law. Change it to match your method.
- A score ranks items against each other. It does not say an item is worth doing.
- Nothing you type is saved or sent.
These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.
Questions
What does MoSCoW stand for?
Must have, Should have, Could have and Won't have this time. The two o's are only there to make the word easy to say.
How much of the work should be Must?
A common guide from the DSDM method is about 60% of the effort, so that the rest can absorb surprises. This tool warns when you pass the limit you set, and when everything is a Must.
How do I calculate a RICE score?
Multiply reach, impact and confidence, then divide by effort. A feature with reach 1,000, impact 2, confidence 80% and effort 4 scores 400. The tool blocks an effort of zero.
What is the difference between RICE and weighted scoring?
RICE has four fixed factors and is common for product features. Weighted scoring lets you choose your own criteria and weights, so it suits decisions such as picking a supplier or a project.
Is anything saved or uploaded?
No. Everything runs in your browser and nothing is stored or sent. Print the result before you leave the page.
Nagi Project Management Suite
Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app, with your project data on your company's own computers.
Read more
Related free tools
- Earned value calculator
Check a project's cost and schedule with earned value: CPI, SPI, forecast at completion and what pace is still needed.
- EAC formula calculator: four estimate at completion methods
Forecast the cost at completion four ways on your own numbers, and see when each method is the right one.
- Project cost-benefit analysis calculator
Test a project's business case year by year: NPV, benefit-cost ratio, payback, IRR and a check on what could change the answer.
- Critical path and PERT calculator
Find the critical path, total and free float, P50 P80 P90 finish days and the chance of finishing by a date, from your task list.