Project cost-benefit analysis calculator
- No sign-up, no email
- Nothing stored
In short
A cost-benefit analysis compares what a project costs with what it returns, with later years counted for less. Enter the costs and benefits for each year and a discount rate, and the calculator gives the net present value, the benefit-cost ratio, the payback, the internal rate of return and how far the benefits can fall before the project stops paying.
Your project, year by year
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Cash flow by year
The first row is year 0, today, and is not discounted. Each row after it is one year later. Type costs and benefits as positive amounts, in one currency.
| Year | Capital cost | Running cost | Benefit | Residual value | Remove |
|---|---|---|---|---|---|
Net present value (NPV)
13,883.36
Worth doing at this discount rate, on these numbers.
- Present value of benefits
- 71,868.78
- Present value of costs
- 57,985.42
- Benefit-cost ratio
- 1.24
- Return on investment (not discounted)
- 50%
- Internal rate of return (IRR)
- 18.03%
- Payback
- 3.13 years
- Discounted payback
- 3.75 years
- Benefits can fall by this much before NPV is 0
- 19.32%
What changes the answer
- Benefits 20% lower
- -490.40 (-14,373.76)
- Benefits 20% higher
- 28,257.12 (+14,373.76)
- Costs 20% higher
- 2,286.28 (-11,597.08)
- Costs 20% lower
- 25,480.44 (+11,597.08)
- Discount rate 2 points higher
- 10,652.59 (-3,230.77)
- Discount rate 2 points lower
- 17,397.82 (+3,514.46)
- Benefits arrive a year late
- 8,559.75 (-5,323.61)
How it is calculated
- Net cash flow of a year
- Benefit plus residual value, minus capital cost and running cost.
- Present value
- A year's amount divided by (1 plus the discount rate) to the power of the year number. Year 0 is today and is not discounted.
- Net present value (NPV)
- Present value of the benefits minus present value of the costs.
- Benefit-cost ratio (BCR)
- Present value of the benefits divided by present value of the costs. Above 1 pays.
- Return on investment
- Total benefits minus total costs, divided by total costs, without discounting.
- Payback
- The year before the running total turns positive, plus what is still owed divided by that year's net cash flow. Discounted payback does the same with each year's net discounted.
- Internal rate of return (IRR)
- The discount rate at which the NPV is exactly zero, found by repeated halving between -99% and 1,000%.
- What changes the answer
- The NPV again with benefits or costs 20% off, the rate 2 points off, and every benefit a year late.
Worked example
- A $50,000 purchase today, then $18,000 of benefit and $2,000 of running cost every year for 5 years, at an 8% discount rate. The net cash flow is $16,000 in each of years 1 to 5.
- Present value of the benefits is $71,869 and of the costs $57,985, so the NPV is $13,883 and the benefit-cost ratio is 1.24.
- The simple payback is 3.13 years and the discounted payback 3.75 years. The IRR is about 18.0%. Benefits could fall about 19% before the NPV reached zero.
What it assumes
- The discount rate is yours. The 8% shown is an example, not advice: use your own cost of capital or the return you could earn elsewhere.
- All amounts are in one currency and in the same year's money. Tax, depreciation and inflation are not included unless you build them into the figures.
- Costs and benefits are typed as positive amounts. A benefit that is hard to price is left out or estimated by you.
- If the cash flow changes sign more than once, the IRR may have more than one answer, and the page says so. NPV is the safer guide.
- Nothing you type is saved or sent. The result is an estimate for planning.
These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.
Questions
How do I do a cost-benefit analysis step by step?
List the costs and the benefits of the project for each year, in one currency. Choose a discount rate. Discount each year back to today and add them up. If the benefits are worth more than the costs today, the project pays. This calculator does the discounting and shows the other measures.
What discount rate should I use?
Your cost of capital, or the return you could earn on the money elsewhere. Try a few: the table of what changes the answer shows the NPV with the rate 2 points higher and lower, so you can see how much the choice matters.
NPV or payback: which matters more?
NPV tells you whether the project creates value over its whole life. Payback tells you how fast the money comes back, which matters when cash is tight or the future is uncertain. A project can have a good NPV and a long payback. Look at both.
What does a benefit-cost ratio below 1 mean?
The present value of the benefits is smaller than the present value of the costs, so the NPV is negative. On the numbers you typed, the project returns less than it costs at that discount rate.
How do I include benefits that are hard to price?
Estimate them as honestly as you can, or leave them out of the figures and note them next to the result. The headroom line shows how far the priced benefits can fall before the NPV reaches zero, which tells you how much the unpriced ones need to be worth.
Nagi Project Management Suite
Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app, with your project data on your company's own computers.
Read more
Related free tools
- Stakeholder analysis grid
Rate stakeholders on power and interest, see the power-interest grid, and get a suggested way to engage each one.
- Project charter builder
Write a project charter section by section, with a budget that adds up and milestones in date order, then print or download it.
- Project status report builder
Build a weekly, monthly or one-page status report with red-amber-green, days late and budget variance.
- Earned value calculator
Check a project's cost and schedule with earned value: CPI, SPI, forecast at completion and what pace is still needed.