Exclusive sale

Up to 64% off yearly and lifetime licenses

Ends December 15, 2026, 23:59 UTC
See the prices
Skip to content
Nagi Software
Cart

Free tool

Earned value calculator

Works in your browser. Nothing you type is sent anywhere or saved.
  • No sign-up, no email
  • Nothing stored

In short

Earned value compares what you planned to have done, what you have actually done and what it cost. The schedule index (SPI) is earned value divided by planned value, and the cost index (CPI) is earned value divided by actual cost. Enter the budget, the percent planned, the percent done and the actual cost, and the calculator gives both indexes and three forecasts at completion.

Where does the project stand?

Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.

The approved budget for the whole project or task.

From your schedule.

%

Measured progress, not time elapsed.

%

A bottom-up figure for the work left. Gives a fourth forecast.

The project is

Behind schedule and over budget

Schedule index 0.8, cost index 0.83. Above 1 is good: below 1 is behind or over.

Planned value (PV)
50,000.00
Earned value (EV)
40,000.00
Actual cost (AC)
48,000.00
Schedule variance (EV - PV)
-10,000.00
Cost variance (EV - AC)
-8,000.00
Schedule performance index (SPI)
0.8
Cost performance index (CPI)
0.83
Forecast at completion, cost stays at today's rate (BAC / CPI)
120,000.00
Forecast, the rest goes to plan
108,000.00
Forecast, cost and schedule both slip (CPI x SPI)
138,000.00
Forecast from your own estimate to complete
n/a
Estimate to complete (first forecast - AC)
72,000.00
Variance at completion (BAC - forecast)
-20,000.00
Index needed to finish on budget (TCPI)
1.15

How it is calculated

Planned value (PV)
The budget at completion times the percent that should be done by now.
Earned value (EV)
The budget at completion times the percent actually done.
Variances
Schedule variance is EV minus PV. Cost variance is EV minus actual cost (AC).
Indexes
Schedule index (SPI) is EV divided by PV. Cost index (CPI) is EV divided by AC. Above 1 is ahead or under budget.
Forecast at completion (EAC)
Three common ways, and your own as a fourth: the budget divided by CPI (cost stays at today's rate); AC plus the work left at budget (the rest goes to plan); AC plus the work left divided by CPI times SPI (cost and schedule both slip). A fourth is AC plus your own estimate to complete.
Estimate to complete and variance
Estimate to complete is the forecast minus AC. Variance at completion is the budget minus the forecast.
To-complete index (TCPI)
The work left divided by the budget left: the cost index you must reach from now on to finish on budget.

Worked example

  • A $100,000 project that should be 50% done is 40% done and has cost $48,000. Planned value is $50,000 and earned value is $40,000.
  • The schedule variance is −$10,000 and the cost variance is −$8,000. SPI is 0.8 and CPI is 0.83: behind schedule and over budget.
  • If cost stays at today's rate, the forecast at completion is $100,000 ÷ 0.8333 = $120,000, which is $20,000 over budget. To finish on budget the rest of the work must run at an index of 1.15.

What it assumes

  • Percent done is measured progress, not time elapsed. The results are only as good as that measurement.
  • The three forecasts assume different things about the rest of the project. None is a prediction: use them as a range.
  • An index shows n/a when its divisor is zero (nothing planned yet, or no cost yet), and any forecast that needs it shows n/a too.
  • One project or task at one date. For several tasks, add their budgets, planned and actual values first.
  • All money is in one currency. The result is an estimate for planning.

These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.

Questions

What do CPI and SPI mean?

CPI is the value of the work done for each unit of money spent: 0.83 means 83 cents of work for every dollar spent. SPI is the work done compared with the work planned by now: 0.8 means 80% of the planned work is done. Above 1 is good for both.

Which forecast at completion should I use?

Use the budget divided by CPI when the cost problem will probably continue. Use the rest-goes-to-plan figure when the overrun was a one-off. Use the CPI times SPI figure when a late schedule also costs money. The spread between them shows how uncertain the forecast is.

What is TCPI?

The cost index you must achieve on the remaining work to finish on budget. Above 1 means you have to do better than you have so far. A figure well above your current CPI is a warning that the budget is out of reach.

Can earned value be negative or above the budget?

No. Earned value runs from zero to the budget, because percent done runs from 0 to 100. Variances can be negative, which means behind schedule or over budget.

Nagi Project Management Suite

Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app, with your project data on your company's own computers.

Read more

Related free tools

All free tools for project managers