Free tool

EAC formula calculator: four estimate at completion methods

Works in your browser. Nothing you type is sent anywhere or saved.
  • No sign-up, no email
  • Nothing stored

In short

The estimate at completion (EAC) is the cost you now expect the whole project to have. There are four standard ways to work it out: the budget divided by CPI, the actual cost plus the work left at budget, the actual cost plus the work left divided by CPI times SPI, and the actual cost plus your own estimate to complete. Enter the numbers and the calculator shows all four side by side.

Where does the project stand?

Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.

The approved budget for the whole project or task.

From your schedule.

%

Measured progress, not time elapsed.

%

A bottom-up figure for the work left. Gives a fourth forecast.

Forecast at completion (EAC), cost stays at today's rate

120,000.00

Four methods are below, each with its own assumption. Schedule index 0.8, cost index 0.83.

Planned value (PV)
50,000.00
Earned value (EV)
40,000.00
Actual cost (AC)
48,000.00
Schedule variance (EV - PV)
-10,000.00
Cost variance (EV - AC)
-8,000.00
Schedule performance index (SPI)
0.8
Cost performance index (CPI)
0.83
Forecast at completion, cost stays at today's rate (BAC / CPI)
120,000.00
Forecast, the rest goes to plan
108,000.00
Forecast, cost and schedule both slip (CPI x SPI)
138,000.00
Forecast from your own estimate to complete
n/a
Estimate to complete (first forecast - AC)
72,000.00
Variance at completion (BAC - forecast)
-20,000.00
Index needed to finish on budget (TCPI)
1.15

The four formulas

1. BAC ÷ CPI
Use when the cost efficiency so far will continue to the end. CPI is earned value divided by actual cost.
2. AC + (BAC − EV)
Use when the overrun so far was a one-off, and the rest of the work will cost what the budget says.
3. AC + (BAC − EV) ÷ (CPI × SPI)
Use when cost and schedule both drive the rest of the cost, for example when a late project needs overtime.
4. AC + your own estimate to complete
Use when the original plan no longer applies and you have a fresh bottom-up estimate of the work left.
Estimate to complete and variance
Estimate to complete is the EAC minus actual cost. Variance at completion is the budget at completion (BAC) minus the EAC.
Index needed to finish on budget (TCPI)
The work left divided by the budget left: (BAC − EV) ÷ (BAC − AC).

Worked example

  • Budget $100,000, planned 50% done, actually 40% done, actual cost $45,000. Earned value is $40,000, the cost index (CPI) is 0.889 and the schedule index (SPI) is 0.8.
  • Method 1 gives $112,500. Method 2 gives $45,000 + $60,000 = $105,000. Method 3 gives $45,000 + $60,000 ÷ (0.889 × 0.8) = $129,375.
  • A bottom-up estimate of $70,000 to finish gives method 4: $115,000. The index needed to finish on budget is $60,000 ÷ $55,000 = 1.09.

What it assumes

  • Percent done is measured progress, not time elapsed. The forecasts are only as good as that measurement.
  • The four methods answer different questions. None is a prediction: use them as a range and say which one you chose.
  • An index shows n/a when its divisor is zero (nothing planned yet, or no cost yet), and the forecasts that need it show n/a too.
  • All money is in one currency. Nothing you type is saved or sent. The result is an estimate for planning.

These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.

Questions

Which EAC formula should I use?

Use BAC divided by CPI when the cost problem will continue. Use actual cost plus the work left at budget when the overrun was a one-off. Use the CPI times SPI version when a late schedule also costs money. Use your own estimate when the plan has changed. Showing two or three together gives a range.

What is the difference between EAC and ETC?

EAC is the cost of the whole project at the end. ETC, the estimate to complete, is only what is still to be spent: EAC minus the actual cost so far.

What does TCPI tell me?

The cost index you must reach on the remaining work to finish on budget. If it is far above your current CPI, the budget is unlikely to hold.

Can earned value be higher than the budget?

No. Earned value is the budget times the percent done, so it runs from zero to the budget. A result above it means the percent done was entered above 100.