Free tool
Critical path and PERT calculator
- No sign-up, no email
- Nothing stored
In short
The critical path is the longest chain of tasks that must finish one after another, and it sets the earliest the project can end. List your tasks with their durations and what each one waits for, and the calculator finds the early and late dates, the float on every task and the critical path. Give three-point estimates and it also gives the chance of finishing by a target day.
Your tasks
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Tasks
Give each task a duration in days, or all three of optimistic, most likely and pessimistic (the three-point estimate is used when all three are filled in). Comes after: the codes of the tasks that must finish first, like A or B, C. Add a lag in days, like A+2 (a gap) or A-1 (an overlap).
| Code | Task | Duration | Optimistic | Most likely | Pessimistic | Comes after | Remove |
|---|---|---|---|---|---|---|---|
Project duration
24.67 days
Critical path: A → C → D → E.
- Spread of the finish date (one standard deviation)
- 2.13 days
- P50: day you finish by with 50% chance
- 24.67
- P80: day you finish by with 80% chance
- 26.46
- P90: day you finish by with 90% chance
- 27.4
- Chance of finishing by day 27
- 86.29%
The chance treats the finish as a normal curve around the project duration with the spread above, following the critical path only. A near-critical path can make it too hopeful.
Dates and float
| Task | Duration | Early start | Early finish | Late start | Late finish | Total float | Free float | Critical |
|---|---|---|---|---|---|---|---|---|
| A · Site setup | 5 | 0 | 5 | 0 | 5 | 0 | 0 | Yes |
| B · Foundations | 5 | 5 | 10 | 6 | 11 | 1 | 1 | No |
| C · Order materials | 6 | 5 | 11 | 5 | 11 | 0 | 0 | Yes |
| D · Frame and roof | 8.67 | 11 | 19.67 | 11 | 19.67 | 0 | 0 | Yes |
| E · Fit-out | 5 | 19.67 | 24.67 | 19.67 | 24.67 | 0 | 0 | Yes |
How it is calculated
- Expected duration (PERT)
- Optimistic plus four times most likely plus pessimistic, divided by six. A task with only a single duration uses that number.
- Variance (PERT)
- The pessimistic minus the optimistic, divided by six, squared.
- Triangular option
- The mean is the optimistic plus most likely plus pessimistic, divided by three. The variance is the squares of the three added up, less the three products of pairs, all divided by 18.
- Forward pass
- A task's early start is the latest early finish of the tasks it comes after (plus any lag). Early finish is early start plus duration.
- Backward pass
- A task's late finish is the earliest late start of the tasks that come after it, minus any lag. Late start is late finish minus duration.
- Total float
- Late start minus early start. A task with no float is critical.
- Free float
- How long a task can slip without delaying the start of any task that comes after it: the smallest gap between its early finish and what those tasks allow.
- P50, P80 and P90
- The project duration plus the number of standard deviations for that chance (0, 0.84 and 1.28) times the spread: the day you finish by with that chance.
- Chance of finishing by a day
- The finish is treated as a normal curve centered on the project duration, with a spread equal to the square root of the variances added up along the critical path.
Worked example
- Tasks: A takes 3 days, B takes 2 days after A, C takes 4 days after A, and D takes 1 day after B and C.
- A finishes on day 3. B runs from day 3 to 5 and C from day 3 to 7. D starts on day 7, when both are done, and ends on day 8.
- The project takes 8 days. The critical path is A, C, D. B could slip by 2 days without delaying anything, so its float is 2.
- A task estimated at 4, 6 and 10 days has a PERT mean of 6.33 and a spread of 1.00. The triangular option gives a mean of 6.67 and a spread of 1.25.
What it assumes
- Time is counted in plain days from day 0, with no calendar. Weekends and holidays are not built in: count working days.
- Every link is finish-to-start: a task starts after the tasks it comes after have finished, plus an optional lag in days.
- The chance of finishing by a day follows the critical path only. A path that is almost critical can make the true chance lower.
- If more than one path has no float, the spread uses the one with the most variance.
- PERT and the triangular option are two ways to turn three estimates into a mean and a spread. Pick the one your method names.
- Nothing you type is saved or sent. The result is an estimate for planning.
These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.
Questions
What is the critical path?
The longest chain of tasks that must run one after another. Any delay to a task on it delays the whole project by the same amount. Tasks off the path have float, which is how long they can slip without delaying the end.
What is float?
The time a task can slip without delaying the project. It is the late start minus the early start. Critical tasks have zero float.
How does a three-point estimate work?
You give an optimistic, a most likely and a pessimistic duration. The expected duration is the optimistic plus four times the most likely plus the pessimistic, all divided by six, which weights the middle estimate most. The gap between optimistic and pessimistic sets the task's variance.
What is the difference between total float and free float?
Total float is how long a task can slip without delaying the end of the project. Free float is how long it can slip without delaying the next task. Total float is shared along a chain of tasks, so free float is never more than total float.
What are P50, P80 and P90?
The day by which you finish with a 50%, 80% or 90% chance, from the spread of your three-point estimates. P80 is a common planning date when you want a margin.
Why does the calculator say there is a loop?
Two or more tasks wait for each other, directly or through others, so none of them can start. Check the Comes after boxes of the tasks it lists and remove one of the links.
Nagi Project Management Suite
Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app, with your project data on your company's own computers.
Read more
Related free tools
- Earned value calculator
Check a project's cost and schedule with earned value: CPI, SPI, forecast at completion and what pace is still needed.
- EAC formula calculator: four estimate at completion methods
Forecast the cost at completion four ways on your own numbers, and see when each method is the right one.
- Project cost-benefit analysis calculator
Test a project's business case year by year: NPV, benefit-cost ratio, payback, IRR and a check on what could change the answer.
- MoSCoW prioritization tool with RICE and weighted scoring
Rank a list with MoSCoW and an effort check, RICE, weighted scoring, impact and effort or Eisenhower.