Project charter builder

Works in your browser. Nothing you type is sent anywhere or saved.
  • No sign-up, no email
  • Nothing stored

In short

A project charter is a short document, signed by the sponsor, that says why a project exists, what it will deliver, when and for how much. Pick a small, medium or large project and the builder shows only the sections that size needs. The budget adds up for you, the milestones are put in date order, and an objective with no number is flagged, and you can print the charter or download it for Word.

Write the charter

Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.

Start from an example:
How big is the project?

Year-month-day.

Why now? What is the situation?

What the project is for, in a sentence or two.

One per line. Each should have a number and a date.

One per line.

One per line. Saying what is out avoids arguments later.

One per line.

One per line.

One per line.

One per line: name and role.

Milestones

Dates as year-month-day. The charter lists them in date order.

Milestones
MilestoneDateRemove

Budget

The total adds up for you.

Budget
ItemAmountRemove

Project charter: Customer portal upgrade

Sponsor: Dana Reyes, Operations Director. Project manager: Tomas Reyes. Start: 4 Jan 2027. Sample format.

Purpose and background

Customers phone us to check an order's status because the portal shows only the last step.

Let customers see the full status of an order themselves, so fewer of them need to call us.

Objectives

  • Cut status calls from 120 a week to 60 by 30 June 2027
  • Show every order step in the portal by 31 March 2027
  • Keep the project within 25,000

Scope

In scope

  • Order timeline in the portal
  • Email when a step changes
  • Training for the support team

Out of scope

  • A new mobile app
  • Changes to the ordering page

Deliverables

  • Order timeline page
  • Status email
  • Support team guide

Milestones

Milestones
11 Jan 2027Kickoff
31 Mar 2027Order timeline built
14 May 2027Support team trained
1 Jun 2027Go live

Budget

Budget
Developer time12,000.00
Email service for a year8,500.00
Contingency4,500.00
Total25,000.00

Main risks

  • Order data has gaps for older orders
  • The supplier of the email service changes its terms

Stakeholders

  • Operations Director (sponsor)
  • Support team
  • Customers

Sponsor and approval

Dana Reyes, Operations Director: signature and date

Tomas Reyes, Project manager: signature and date

How it works

Budget total
The budget lines added up, in whole cents.
Milestones
Sorted by date. One dated before the start date, or without a date, is flagged.
Objectives
An objective with no number or date is flagged, and one with a vague word such as improve or reduce and no number asks for how much and by when.
Sizes
Small keeps six sections: purpose, objectives, scope, milestones, budget and approval. Medium adds deliverables, risks and stakeholders. Large adds assumptions.

Worked example

  • A budget of $12,000 for developer time, $8,500 for an email service and $4,500 of contingency totals $25,000.
  • The objective Improve customer satisfaction is flagged. Cut status calls from 120 a week to 60 by 30 June 2027 is not.
  • A milestone dated before the project's start date, such as a site survey in December for a January start, is flagged so you can fix the date or the start.

What it assumes

  • The charter is text you write. The builder lays it out, adds up the budget and checks the dates: it does not judge whether the project is a good idea.
  • Nothing you type is saved or sent. Print it or download it before you leave the page.
  • The examples are only examples. Sample format. Check it fits your organization's rules and your contract.

Review the text and adjust it to your own policies and contract before you send or sign it.

Questions

What is a project charter and who signs it?

A short document that authorizes a project and states its purpose, objectives, scope, milestones and budget. The sponsor signs it, and often the project manager too. It is the reference point when scope or cost starts to drift.

What is the difference between a charter, a project plan and a scope statement?

The charter says why and what at a high level and gives the go-ahead. The plan says how, in detail: tasks, dates, resources. The scope statement is a part of the charter or the plan that lists what is in and out.

How long should a charter be?

One page for a small project, two to four for a large one. If the sponsor will not read it in five minutes, it is too long. The size switch shows only the sections each size needs.

What makes a good project objective?

It says what will change, by how much and by when, so that anyone can tell afterwards whether it was met. The builder flags an objective with no number and asks for one.

Can I turn the charter into a project plan?

The charter's scope, milestones and budget are the starting point for a plan. Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app.