Riverside Retail Unit: status report
Week ending 20 November 2026 · Prepared by Tomas Reyes
Overall: Amber: at risk · stable · 38% complete
| Area | Status | Comment |
|---|---|---|
| Scope | Green: on track | No change requests this week. |
| Schedule | Amber: at risk | Steel late; schedule under review. |
| Budget | Amber: at risk | Forecast 2.4% over; contingency covers it. |
| Risks | Amber: at risk | Two open, both with owners. |
Budget 500,000.00; spent 186,000.00 (37.2%); forecast 512,000.00; variance +12,000.00 (2.4%).
| Milestone | Planned | Forecast | Days late |
|---|---|---|---|
| Foundations complete | 13 Nov 2026 | Done | |
| Steel frame up | 18 Dec 2026 | 30 Dec 2026 | 12 |
| Weathertight | 19 Feb 2027 | 26 Feb 2027 | 7 |
Done this period
- Slab poured and cured
- Steel delivery date confirmed for 7 December
- Permit conditions closed out
Next period
- Start steel erection
- Issue the revised schedule to the owner
- Hold the monthly cost review
Top risks and issues
- Steel delivery is 12 days later than planned
- Rain forecast for the week of the roof deck
Decisions needed
- Owner to approve the revised schedule by 27 November
Sample format. The suggested statuses use thresholds you can ignore: you decide the status of each area.