Free tool
Stakeholder analysis grid
- No sign-up, no email
- Nothing stored
In short
Stakeholder analysis sorts the people affected by a project, or able to affect it, by how much power they have and how much interest they take. High on both means manage closely, high power and low interest means keep satisfied, low power and high interest means keep informed, and low on both means monitor. Rate your stakeholders from 1 to 5 and the grid fills in.
Stakeholder grid
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Stakeholders
Power is how much they can affect the project. Interest is how much it affects them. Rate each 1 (low) to 5 (high).
| Name | Role | Power | Interest | Attitude now | What they expect | Remove |
|---|---|---|---|---|---|---|
3 by default: 4 and 5 are high.
Stakeholder grid: Riverside Retail Unit
Keep satisfied
City inspector
Manage closely
Riverside Holdings
Monitor
Brick supplier
Keep informed
Mrs Ahmed
Higher up is more power. To the right is more interest.
| Stakeholder | Power / interest | Where | How to engage | Expects |
|---|---|---|---|---|
| Riverside Holdings (Owner) | 5 / 5 | Manage closely | Involve them in decisions and talk often, one to one. | On time, on budget, no surprises |
| Mrs Ahmed (Neighbor) | 2 / 4 | Keep informed | Send regular updates and listen to their feedback. | Little noise and dust, clear hours |
| City inspector (Building inspector) | 5 / 2 | Keep satisfied | Keep them comfortable with short, focused updates before decisions. | Work to the approved plans |
| Brick supplier (Supplier) | 2 / 2 | Monitor | Watch for changes and send occasional general updates. | Orders with enough notice |
Sample format. Ratings are your judgment.
Communication plan from the grid
One click writes a starting row for each stakeholder from where they sit on the grid. Then edit any box.
Communication plan
| Audience | Message | Channel | How often | Owner | Remove |
|---|---|---|---|---|---|
| None yet. | |||||
How it works
- Power and interest
- Each rated 1 (low) to 5 (high) by you. Power is how much they can affect the project. Interest is how much it affects them.
- The four boxes
- Above the line on both: manage closely. Power above, interest not: keep satisfied. Interest above, power not: keep informed. Neither: monitor.
- The line
- Ratings above 3 count as high. You can move the line between 1 and 4.
- Who to talk to first
- People in the manage-closely box, resistant ones first, then by power.
Worked example
- The owner has power 5 and interest 5: manage closely. The neighbor has power 2 and interest 4: keep informed. The building inspector has power 5 and interest 2: keep satisfied. The brick supplier has power 2 and interest 2: monitor.
- A neighbor who is resistant is still in the keep informed box, but the plan starts that row with listening to their concerns.
What it assumes
- Ratings are your judgment. Agree them with the team and update them when the project changes.
- The suggested engagement is a starting point, not a rule. Edit it for the person.
- Nothing you type is saved or sent. Print or download the grid before you leave the page. Sample format. Check it fits your policy and local rules.
Review the text and adjust it to your own policies and contract before you send or sign it.
Questions
What is stakeholder analysis and why do it?
It is listing who is affected by a project or can affect it and deciding how much attention each needs. Without it, the loud voices get the attention and the quiet powerful ones are missed until they object.
How do I decide who is high power?
Ask whether they can stop, change or fund the project: an owner, a regulator, a lender, a key supplier. Someone who can affect the outcome only a little is low power, however much they care.
Stakeholder register or stakeholder analysis: what is the difference?
A register is the list of stakeholders with their details. The analysis rates them and decides how to engage each one. This page keeps both in one table.
How often should I update the register?
At each phase of the project and whenever someone new joins or an attitude changes. A stale grid is worse than none, because it tells you who to ignore.
Can I turn the grid into a communication plan?
Yes. The communication plan builder on this site writes a starting row for each stakeholder from where they sit on the grid.
Nagi Project Management Suite
Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app, with your project data on your company's own computers.
Read more
Related free tools
- Project cost-benefit analysis calculator
Test a project's business case year by year: NPV, benefit-cost ratio, payback, IRR and a check on what could change the answer.
- Risk register and risk matrix generator
Score risks by probability and impact, see the heat map before and after your response, and work out expected monetary value, then keep a RAID log and lessons learned.
- Communication plan builder
Turn a stakeholder list into a communication plan with the audience, message, channel, frequency and owner for each row.
- Earned value calculator
Check a project's cost and schedule with earned value: CPI, SPI, forecast at completion and what pace is still needed.