Risk register and risk matrix generator

Works in your browser. Nothing you type is sent anywhere or saved.
  • No sign-up, no email
  • Nothing stored

In short

A risk register lists each risk with how likely it is, how much it would hurt, who owns it and what you will do. A risk's score is its probability times its impact, and the matrix shows where each one sits. Enter your risks on a 3 by 3 or 5 by 5 scale, set your own band edges, and the generator draws the heat map before and after your response.

Risk register and matrix

Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.

Matrix size

Band edges (scores up to each)

Above is extreme. Highest score 25.

There is no single standard for the bands: these are examples. Set your own.

Risks

Score each from 1 to 5: probability 1 rare, 2 unlikely, 3 possible, 4 likely, 5 almost certain; impact 1 insignificant, 2 minor, 3 moderate, 4 major, 5 catastrophic. "After" is the score once your response is in place.

Risks
IDRiskOwnerProbabilityImpactResponseProbability afterImpact afterRemove
Show the matrix

Risk register

5 Almost certain
5
10
15
20
25
4 Likely
4
8
12
16R1
20
3 Possible
3
6
9R2
12
15
2 Unlikely
2
4
6
8R4
10
1 Rare
1
2
3
4
5R3
1 Insignificant
2 Minor
3 Moderate
4 Major
5 Catastrophic
Low: 0Medium: 3High: 1Extreme: 0
Risks, highest score first
IDRiskOwnerScoreResponseScore after
R1Late steel deliveryProcurement4 × 4 = 16 (High)Mitigate8 (Medium)
R2Rain delays the slab pourSite manager3 × 3 = 9 (Medium)Accept–
R4Permit comes lateProject manager2 × 4 = 8 (Medium)Mitigate4 (Low)
R3Subcontractor goes into liquidationCommercial1 × 5 = 5 (Medium)Transfer3 (Low)

Sample format. Scales and bands are the ones set on this page.

Expected monetary value and reserve

Threats and opportunities

Expected value is the chance times the money. A threat counts against you and an opportunity for you.

Threats and opportunities
ItemTypeChance %Cost or savingRemove
Expected cost of the threats (the reserve)
8,500.00
Expected value of the opportunities
1,000.00
Net exposure
7,500.00

RAID log and lessons learned

RAID stands for risks, assumptions, issues and dependencies. Risks are in the register above. Add the rest here, with actions and the lessons you learn on the way, and print one log for the project file.

Log

Issues

A problem that has already happened, as opposed to a risk that might. Give it an owner and a next step.

Issues
RefIssueOwnerPriorityNext stepStatusRemove

RAID log and lessons learned

Risks

Risks
IDRiskOwnerScoreResponse
R1Late steel deliveryProcurement4 × 4 = 16Mitigate
R2Rain delays the slab pourSite manager3 × 3 = 9Accept
R3Subcontractor goes into liquidationCommercial1 × 5 = 5Transfer
R4Permit comes lateProject manager2 × 4 = 8Mitigate

Assumptions

Assumptions
RefAssumptionWho confirms itBy whenStatus
A1The client signs off the drawings by 15 JanuaryProject manager2027-01-15Open
A2The crane is free for the first two weeks of MarchSite manager2027-02-01In progress

Issues

Issues
RefIssueOwnerPriorityNext stepStatus
I1Steel delivery is two weeks lateProcurementHighAsk the supplier for a firm dateOpen

Dependencies

Dependencies
RefWhat we depend onFrom whomNeeded byStatus
D1Utility connection before commissioningUtility company2027-04-01Open

Actions

Actions
RefActionOwnerDueStatus
X1Send the revised schedule to the clientProject manager2026-12-04In progress

Lessons learned

Lessons learned
AreaWhat happenedWhat we learnedNext timeOwner
ProcurementLong-lead steel was ordered after the design frozeLead time was longer than the floatOrder long-lead items at the concept stageProcurement
CommunicationWeekly report went out late twiceNobody owned itName an owner and a dayProject manager

Sample format. Check it fits your project rules.

How it is calculated

Risk score
Probability times impact, each on a scale of 1 to 3 or 1 to 5.
Band
Low up to the first edge you set, medium up to the second, high up to the third and extreme above it.
Score after the response
Probability times impact again, using the scores you expect once your response is in place.
Expected monetary value
The chance (0 to 100%) times the money it would cost or save. Threats count against you, opportunities for you.
RAID log
Risks, assumptions, issues and dependencies kept in one place, with actions and lessons learned: a list with an owner and a status on each line, and no arithmetic.
Reserve and net exposure
The reserve is the expected cost of the threats. Net exposure is the threats' expected cost minus the opportunities' expected value.

Worked example

  • Late steel delivery: probability 4 (likely) times impact 4 (major) is a score of 16, which is high. After you order early, probability drops to 2: 2 × 4 = 8, which is medium.
  • A rain delay with a 30% chance of costing $20,000 has an expected cost of $6,000. A 50% chance of a $5,000 permit increase adds $2,500, and a sure $1,000 saving counts for you. The net exposure is $6,000 + $2,500 − $1,000 = $7,500.

What it assumes

  • There is no single standard for the scales or the bands. The edges shown are examples; set the ones your company or your client uses.
  • Scores are whole numbers from 1 to the size of the matrix. Words such as likely or major are guides; agree what they mean in your team before you score.
  • The generator scores what you type. It does not tell you which risks you have missed.
  • Expected monetary value treats each item on its own. It does not model risks that depend on each other.
  • Nothing you type is saved or sent. Print the register or download the CSV before you leave the page.

Review the text and adjust it to your own policies and contract before you send or sign it.

Questions

How do I score a risk?

Give it a probability and an impact on the same scale, then multiply them. A likely (4) risk with a major (4) impact scores 16. Compare the score with your bands to see whether it is low, medium, high or extreme, and spend your effort on the high ones.

What is the difference between inherent and residual risk?

The inherent score is the risk as it stands today. The residual score is what is left once your response is in place: a new supplier, an earlier order, insurance. Scoring both shows whether your response is worth its cost.

What counts as a high risk on a 5 by 5 matrix?

That is your call: no standard exists. The example bands treat 10 to 16 as high and above 16 as extreme. Many teams use their own edges. Change the three band numbers on the page and the heat map follows.

What is the difference between a risk and an issue?

A risk may happen, so it has a probability. An issue has happened and needs an action now. When a risk occurs, move it to your issues list and give it an owner and a date.

What is a RAID log?

RAID stands for risks, assumptions, issues and dependencies. It is one list that keeps them together, with an owner and a status on each line. This page adds actions and lessons learned, and prints the whole log for the project file.

How often should I update the register?

Often enough that the scores are still true: at every project meeting for a fast job, monthly for a slow one, and whenever something big changes. Update the owner, the score and the response each time.

Nagi Project Management Suite

Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app, with your project data on your company's own computers.

Read more

Related free tools

  • Stakeholder analysis grid

    Rate stakeholders on power and interest, see the power-interest grid, and get a suggested way to engage each one.

  • Skills matrix builder

    Rate people on skills against a target level and find the gaps, who can cover, and the skills only one person has.

  • Training and certification matrix

    Track who has done which course and certificate, what is about to expire, and what is overdue, with a due list.

  • Earned value calculator

    Check a project's cost and schedule with earned value: CPI, SPI, forecast at completion and what pace is still needed.

All free tools for project managers