Communication plan builder
- No sign-up, no email
- Nothing stored
In short
A communication plan says who is told what, how, how often and by whom. List your stakeholders and rate their power and interest, and one click writes a starting row for each from where they sit on the grid: weekly meetings for the people to manage closely, a monthly summary for those to keep satisfied, and so on. Edit any box, then print the plan or download it for Word.
1. List your stakeholders
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Stakeholders
Power is how much they can affect the project. Interest is how much it affects them. Rate each 1 (low) to 5 (high).
| Name | Role | Power | Interest | Attitude now | What they expect | Remove |
|---|---|---|---|---|---|---|
3 by default: 4 and 5 are high.
Stakeholder grid: Riverside Retail Unit
Keep satisfied
City inspector
Manage closely
Riverside Holdings
Monitor
Brick supplier
Keep informed
Mrs Ahmed
Higher up is more power. To the right is more interest.
| Stakeholder | Power / interest | Where | How to engage | Expects |
|---|---|---|---|---|
| Riverside Holdings (Owner) | 5 / 5 | Manage closely | Involve them in decisions and talk often, one to one. | On time, on budget, no surprises |
| Mrs Ahmed (Neighbor) | 2 / 4 | Keep informed | Send regular updates and listen to their feedback. | Little noise and dust, clear hours |
| City inspector (Building inspector) | 5 / 2 | Keep satisfied | Keep them comfortable with short, focused updates before decisions. | Work to the approved plans |
| Brick supplier (Supplier) | 2 / 2 | Monitor | Watch for changes and send occasional general updates. | Orders with enough notice |
Sample format. Ratings are your judgment.
2. Build the communication plan
One click writes a starting row for each stakeholder from where they sit on the grid. Then edit any box.
Communication plan
| Audience | Message | Channel | How often | Owner | Remove |
|---|---|---|---|---|---|
| None yet. | |||||
How it works
- Where each person sits
- Power and interest above your line give manage closely, power only gives keep satisfied, interest only gives keep informed, and neither gives monitor.
- The starting row
- Manage closely: weekly, by meeting or call. Keep satisfied: monthly, a short email summary. Keep informed: every two weeks, an email or noticeboard. Monitor: quarterly, a newsletter or website.
- A resistant stakeholder
- The message starts with listening to their concerns and answering them.
Worked example
- The owner (power 5, interest 5) gets a weekly meeting or call about progress, decisions and risks. The inspector (power 5, interest 2) gets a monthly email summary.
- The neighbor (power 2, interest 4, resistant) gets an update every two weeks that starts by listening to their concerns. The supplier gets a quarterly newsletter.
What it assumes
- The starting rows are defaults to edit, not rules. Change the channel, the timing and the message to suit the person.
- Ratings are your judgment. Agree them with the team and update them as the project changes.
- Nothing you type is saved or sent. Print or download the plan before you leave the page. Sample format. Check it fits your policy and local rules.
Review the text and adjust it to your own policies and contract before you send or sign it.
Questions
What should a communication plan contain?
For each audience: what they need to hear, how you will tell them, how often and who is responsible. Add the date of the next update. A plan with no owner for a row is a plan that does not happen.
How often should I communicate with stakeholders?
As often as their power and interest justify. A weekly call suits the sponsor and a quarterly note suits a distant supplier. Ask each person how often they want to hear, and tell them how they can reach you.
Can I download the plan?
Yes. Print it or save it as a PDF from the print window, download it for Word, or download the rows as a CSV file for a spreadsheet.
Is my data saved or uploaded?
No. The plan is built in your browser and nothing is stored or sent. Print or download it before you close the page.
Nagi Project Management Suite
Nagi Project Management Suite covers scheduling, resources, time, cost, risk and reporting in one Windows app, with your project data on your company's own computers.
Read more
Related free tools
- Stakeholder analysis grid
Rate stakeholders on power and interest, see the power-interest grid, and get a suggested way to engage each one.
- Earned value calculator
Check a project's cost and schedule with earned value: CPI, SPI, forecast at completion and what pace is still needed.
- EAC formula calculator: four estimate at completion methods
Forecast the cost at completion four ways on your own numbers, and see when each method is the right one.
- Project cost-benefit analysis calculator
Test a project's business case year by year: NPV, benefit-cost ratio, payback, IRR and a check on what could change the answer.