Job cost report and cost to complete calculator

Works in your browser. Nothing you type is sent anywhere or saved.
  • No sign-up, no email
  • Nothing stored

In short

A job cost report compares, for every cost code, the budget with what is committed, what has been spent and what you still expect to spend. Add the contract and what you have billed, and the calculator gives the forecast final cost, the percent complete, the revenue earned, any over or under billing and the margin the job is heading for. Percent complete uses the forecast, not the original budget.

Job cost report

Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.

Cost codes

Cost to complete is your estimate to finish the code. Leave it blank and the forecast is the largest of budget, committed and actual.

Cost codes
Cost codeBudgetCommittedActual to dateCost to completeRemove

With approved change orders.

Forecast final cost

169,200.00

9,200.00 over the 160,000.00 budget. Projected margin 15.4% against a planned 20%.

Actual to date
99,200.00
Percent of budget spent
62%
Percent complete (actual ÷ forecast)
58.63%
Earned revenue
117,257.68
Billed to date
120,000.00
Over billed
2,742.32
Projected profit
30,800.00

Percent complete is actual cost divided by forecast final cost, not by the original budget. Raise a forecast and percent complete falls.

Job cost report

Budget, committed, actual and forecast by cost code
Cost codeBudgetCommittedActualCost to completeForecastVariance% spent
03 Concrete30,000.0030,000.0028,500.001,500.0030,000.000.0095%
06 FramingForecast is over budget42,000.0040,000.0036,200.009,800.0046,000.00-4,000.0086.19%
09 FinishesForecast is over budget38,000.0022,000.0014,500.0030,500.0045,000.00-7,000.0038.16%
26 Electrical50,000.0036,000.0020,000.0028,200.0048,200.001,800.0040%
Total160,000.00128,000.0099,200.0070,000.00169,200.00-9,200.0062%

Contract 200,000.00. Percent complete 58.63% by cost to cost. Variance is budget minus forecast: negative is over budget. Sample format.

Job cost sheet (cost accounting)

Material, labor and applied overhead for one job or batch, and what each unit cost. For coursework or a shop that costs jobs this way.

Overhead is applied to
% of direct labor

Total job cost

32,000.00

160.00 a unit.

Direct material
12,000.00
Direct labor
8,000.00
Overhead applied
12,000.00
Total
32,000.00

How it is calculated

Forecast final cost of a code
Actual to date plus your cost to complete. With no cost to complete typed, the largest of budget, committed and actual.
Variance
Budget minus forecast. Negative means over budget.
Percent complete
Total actual to date divided by total forecast final cost, as a percentage: the cost-to-cost method.
Earned revenue
The contract sum times percent complete.
Over or under billing
Billed to date minus earned revenue. Positive is over billed, negative is under billed.
Projected profit and margin
The contract minus the total forecast final cost, and that divided by the contract.

Worked example

  • A $200,000 contract with a $160,000 budget. $99,200 has been spent, which is 62% of the budget, and you now expect $70,000 more to finish.
  • The forecast final cost is $99,200 + $70,000 = $169,200, which is $9,200 over budget. Percent complete is $99,200 ÷ $169,200 = 58.6%, not 62%.
  • Earned revenue is 58.6% of $200,000 = $117,258. With $120,000 billed, the job is over billed by $2,742. The projected margin is 15.4% against a planned 20%.

What it assumes

  • Percent complete is by cost to cost. A higher forecast lowers it, because the same cost to date is a smaller share of a bigger job.
  • Committed cost is shown and used for the forecast only when you give no cost to complete: it is a floor, not a prediction.
  • Accounting treatment differs by country and by business. This is arithmetic on the figures you type, not an accounting opinion: ask your accountant how to book it.
  • The cost-accounting job cost sheet at the bottom costs one job or batch from material, labor and applied overhead.
  • Nothing you type is saved or sent. The result is an estimate for planning.

These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.

Questions

How do I calculate percent complete in construction?

By the cost-to-cost method, divide the cost to date by the forecast final cost, which is the cost to date plus what you expect to spend to finish. $99,200 spent with $70,000 to go is 58.6% complete, not the 62% you get by dividing by the original budget.

What is cost to complete and who sets it?

It is your estimate of what you still have to spend to finish a cost code. The project manager sets it from the work left, the quotes in hand and what has been committed, and updates it each month. An out-of-date figure is the usual reason a WIP schedule is wrong.

What are over billing and under billing?

Over billing means you have billed more than the work has earned. Under billing means the work has earned more than you have billed. The WIP calculator on this site shows the same figures for several jobs at once.

Why does my percent complete fall when my forecast rises?

Because percent complete is the cost to date as a share of the forecast. If you raise the forecast, the same cost to date is a smaller share of it. It is the reminder that a job cannot be called further along simply because more money has been spent.

What goes on a job cost sheet?

In cost accounting, the direct material, the direct labor and the overhead applied to one job, added up, and divided by the units produced for a cost per unit. The section at the bottom of this page does that.