Free tool
Equipment cost per hour calculator
- No sign-up, no email
- Nothing stored
In short
What a machine costs per hour is its fixed costs of owning, spread over the hours you use it, plus what it costs to run. Enter the price, the value when you sell, the years you keep it, the hours a year and your running costs. The result shows the cost per hour, how it changes with use and the hours a year above which owning is cheaper than renting.
Cost to own and run it
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Cost per hour
66.20
18.20 to own plus 48.00 to run.
- Depreciation a year
- 20,000.00
- Interest a year
- 4,200.00
- Insurance, taxes, storage a year
- 2,100.00
- Fixed costs a year
- 27,300.00
If you used it more or less
- 500 hours a year
- 102.60 per hour
- 1,000 hours a year
- 75.30 per hour
- 1,500 hours a year
- 66.20 per hour
- 2,000 hours a year
- 61.65 per hour
- 2,500 hours a year
- 58.92 per hour
Owning costs less than renting above about 580.85 hours a year.
How it is calculated
- Depreciation
- The price less the value when you sell it, divided by the years you keep the machine.
- Interest and insurance
- The percentages you type, taken on the average investment: the price plus the sale value, divided by two.
- Cost to own per hour
- Depreciation, interest, insurance and other fixed costs of a year, divided by the hours used in a year.
- Cost to run per hour
- Fuel used times the fuel price, plus repairs, plus the operator's wage.
- Break-even hours
- The fixed costs of a year divided by the rental price per hour less the running cost per hour.
Worked example
- A $120,000 machine sold for $20,000 after 5 years loses $20,000 a year. At 6% interest and 3% insurance on the $70,000 average investment, plus $1,000 of other costs, the fixed costs are $27,300 a year, or $18.20 an hour at 1,500 hours.
- With running costs of $48 an hour the cost is $66.20. Against a $95 rental, owning pays off above about 581 hours a year.
What it assumes
- Every rate is yours. No fuel prices, rental rates or depreciation schedules are built in.
- Depreciation is straight line over the years you keep the machine. Tax depreciation follows different rules.
- Interest is worked out on the average investment, a standard way to approximate the money tied up over the life.
- Nothing you type is saved or sent.
These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.
Questions
How do I calculate equipment cost per hour?
Add the fixed costs of a year (depreciation, interest, insurance and other fixed costs) and divide by the hours used. Then add the cost to run it for an hour: fuel, repairs and the operator.
How does the number of hours affect the cost?
The more hours you use a machine, the less each hour carries of the fixed cost. The table on this page shows the cost per hour at different amounts of use.
When is owning cheaper than renting?
When you use the machine enough that the fixed costs per hour, plus running costs, fall below the rental price. The break-even figure shows the hours a year where that happens.
Can I use this for a truck or van?
Yes. Switch to cost per mile and use miles a year. Leave the operator blank to cost the vehicle without the driver.
Is anything saved or uploaded?
No. Everything runs in your browser and nothing is stored or sent.
Nagi Construction Management Suite
Nagi Construction Management Suite keeps budget, committed, actual and forecast cost for every cost code.
Read more
Related free tools
- Subscription vs one-time license calculator
Compare a per-user subscription with a one-time license year by year, and see when the subscription catches up.
- Draw schedule and cost-plus calculator
Build a draw schedule with retainage, work out interest on loan draws and price a cost-plus job.
- Job cost report and cost to complete calculator
Turn budget, committed and actual cost by cost code into a forecast, percent complete, earned revenue and projected margin.
- Labor hours and productivity calculator
Work out labor hours, man hours, crew days and cost from a quantity and your own output rate, then check productivity.