What is a draw schedule?+
It is a list of when and how much the contractor bills, usually tied to milestones such as foundations or handover, with the retainage held on each draw.
How do I calculate a cost-plus price?+
Add the fee to the cost. A 15% fee on $330,000 is $49,500, so the price is $379,500. A fixed fee is simply added to the cost.
Is a cost-plus fee the same as a margin?+
No. A 15% fee on cost is 13.04% of the price, because the price is larger than the cost. Quote the fee on the base you mean.
What does a maximum price do?+
It caps what the owner pays. If the work costs less, the saving is usually shared; if it costs more, the contractor carries the difference. Your contract sets how.
How is interest on a construction loan worked out?+
Interest is charged on what has been drawn, not on the full loan. Take the balance drawn, times the yearly rate, times the days it is outstanding, divided by 360 or 365 as your lender does. $200,000 drawn at 7% for 30 days is $1,166.67 on a 360-day year and $1,150.68 on a 365-day year.
How is a maximum price shared when costs come in under it?+
The saving is the maximum less cost plus fee, and it is split as you type. With a cost of $330,000, a 15% fee (price $379,500), a $400,000 maximum and a 50% share for the contractor, the saving is $20,500, the contractor's share is $10,250 and the owner pays $389,750. If the maximum were $370,000, the owner would pay $370,000 and the contractor would carry the $9,500 over it.
How should I choose the milestones for a draw schedule?+
Tie each draw to a milestone that someone can see and check, such as foundations, framing, rough-in, finishes and handover. Too few milestones makes each draw large, and too many makes each one a chore. Your lender or contract may set the milestones for you.
Is anything saved or uploaded?+
No. Everything runs in your browser and nothing is stored or sent.