Work in progress schedule
As of —. Percent complete by the cost-to-cost method. Sample format.
| Job | Contract | Est. total cost | Cost to date | % complete | Earned | Billed | Over billed | Under billed | Gross profit at completion |
|---|---|---|---|---|---|---|---|---|---|
| Riverside Retail Unit | 1,000,000.00 | 800,000.00 | 400,000.00 | 50% | 500,000.00 | 450,000.00 | – | 50,000.00 | 200,000.00 (20%) |
| Northgate Warehouse | 300,000.00 | 250,000.00 | 200,000.00 | 80% | 240,000.00 | 290,000.00 | 50,000.00 | – | 50,000.00 (16.67%) |
| Elm Street Fit-outExpected loss 18,000.00 | 180,000.00 | 198,000.00 | 99,000.00 | 50% | 90,000.00 | 70,000.00 | – | 20,000.00 | -18,000.00 (-10%) |
| Total (3 jobs) | 1,480,000.00 | 1,248,000.00 | 699,000.00 | – | 830,000.00 | 810,000.00 | 50,000.00 | 70,000.00 | 232,000.00 |
- Backlog (contract not yet earned)
- 650,000.00
- Cost to complete
- 549,000.00
- Gross profit earned to date
- 131,000.00
Over billed means billed ahead of the work earned. Under billed means the work earned is ahead of the billing.