Construction contingency and escalation calculator

Works in your browser. Nothing you type is sent anywhere or saved.
  • No sign-up, no email
  • Nothing stored

In short

Contingency is money held back for what the estimate cannot see, and escalation is the allowance for prices rising before you buy. A 10% contingency means two different amounts depending on whether it is 10% of the base cost or 10% of the total budget, so this calculator shows both. It then compounds your own rates to the middle of construction and tracks how fast the contingency is being used.

Contingency: of the base or of the total

Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.

%

I know the base cost

Contingency
90,000.00
Budget with contingency
990,000.00

I know the total budget

If 10% is of the total: base
900,000.00
and contingency
100,000.00
If 10% is on top of the base: base
909,090.91
and contingency
90,909.09

The two readings differ, so write down which one your contract and your client use.

Contingency against progress

%

For the cover against work left.

Contingency left

200,000.00

60% used. An even draw would have used 200,000.00 by now; you are 100,000.00 above that.

Pace
Drawing faster than the work
Contingency left as a share of the work left
6.67%

An even draw is a plain yardstick for a warning, not a forecast. Risks are rarely spread evenly.

Escalation to the middle of construction

If the estimate is priced today and building runs from month 6 to month 18, the mid-point is month 12: 1 year.

years

Cost by category

Type the rate you expect for each category. No index data is built in.

Cost by category
CategoryCost at today's pricesYearly rate %Remove

Escalation allowance

790,405.01

7.9% on 10,000,000.00 gives 10,790,405.01 after 1.5 years of compounding.

Labor
4,242,384.24 (+242,384.24)
Materials
6,548,020.77 (+548,020.77)

Price adjustment from an index

%
%
%

Price adjustment

50,000.00

Index change 10%, on the adjustable share only.

Adjusted price
1,050,000.00

Type the index values from the source your contract names. Check the clause in your contract for how the adjustment is worked out.

How it is calculated

Contingency on the base
Base cost times the percentage. The budget is the base plus that.
Contingency from a total
Of the total: the total times the percentage. On top of the base: the total divided by one plus the percentage gives the base.
Escalation
Cost at today's prices times one plus the yearly rate, to the power of the years to the mid-point of construction.
Index adjustment
Price times the adjustable share times the change in the index since the base date, with an optional cap and floor on the change.
Burn-down
Contingency times the percent complete is what an even draw would have used. The gap to what has been drawn shows whether it is going faster or slower than the work.

Worked example

  • A total budget of $1,000,000 with 10% contingency is a $900,000 base plus $100,000 if the 10% is of the total. If it is 10% on top of the base, it is a $909,091 base plus $90,909.
  • $10,000,000 escalated at 5% a year for 3 years is $11,576,250, an allowance of $1,576,250.

What it assumes

  • No benchmark percentages and no published cost indices are built in. Every rate and index value is the one you type, from the source your contract names.
  • Escalation is compounded yearly to the middle of the construction period, the usual way to approximate spending over time.
  • An even draw of contingency is a rule of thumb for a warning, not a forecast. Risks are rarely spread evenly.
  • Check the escalation or price adjustment clause in your contract for how it is worked out.
  • Nothing you type is saved or sent.

These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.

Questions

How much contingency should a construction project carry?

There is no single answer. It depends on how complete the design is, the type of work and how much risk you hold. Set the percentage from your own history or your client's rules, then see the amount here.

Is a 10% contingency 10% of the base cost or of the total?

Both are used, and they give different money. On a $1,000,000 total, 10% of the total is $100,000 while 10% on top of the base is $90,909. Say which one you mean in the budget.

How do I calculate escalation in a construction estimate?

Compound the yearly rate for each category, such as labor and materials, from the date of the estimate to the middle of construction. $10,000,000 at 5% for 3 years becomes $11,576,250.

What is the mid-point of construction?

The date halfway through the building period. Costs are bought over the whole job, so the middle date is a fair single point for the allowance.

Is anything saved or uploaded?

No. Everything runs in your browser and nothing is stored or sent.