Change order form generator

Works in your browser. Nothing you type is sent anywhere or saved.
  • No sign-up, no email
  • Nothing stored

In short

A change order records extra or changed work, what it costs and who agreed to it. Describe the change, price it from labor, materials, equipment and subcontractors with your markup, and the generator lays out a form with the build-up, the new contract sum and signature lines. Print it or save it as a PDF.

Fill in the change order

Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.

About this change order
Direct costs and markup

Wage plus burden.

%
%
%
%
Bond, insurance and delay
% of subtotal

Site overhead for each extra day.

The contract (optional)

Their total, approved so far.

Change order price

6,761.80

1,459.00 above direct cost (21.58% of the price).

Labor: 1,102.80 + 15%
1,268.22
Materials: 2,400.00 + 15%
2,760.00
Subcontractors: 1,800.00 + 8%
1,944.00
Subtotal with markup
5,972.22
Bond or insurance
89.58
Delay overhead
700.00
Change order price
6,761.80
Direct cost
5,302.80
Markup earned
669.42

Bond and delay overhead recover costs, so they are not counted as markup.

Your change order, ready to print

Change order

Sample format. Check it fits your contract and local rules.

Number
CO-003
Date
30 November 2026
To (owner)
Riverside Holdings
From (contractor)
Kestrel Builders
Project
Riverside Retail Unit
Reason
Owner request

Description of the change

Supply and install six additional interior doors on the first floor, as requested by the owner on 24 November 2026.

Cost of the change
ItemCostMarkupPrice
Labor1,102.8015%1,268.22
Materials2,400.0015%2,760.00
Subcontractors1,800.008%1,944.00
Subtotal5,972.22
Bond or insurance89.58
Delay overhead (2 days)700.00
Change order price6,761.80
Days added to the schedule
2

Owner: approved, signature and date

Contractor: signature and date

How the price is built

Labor cost
Hours times the burdened hourly rate (the wage plus its burden).
Line price
The line's cost plus its cost times its markup. Labor, materials, equipment and subcontractors each have their own markup.
Bond or insurance
The subtotal of the line prices times the bond percentage.
Delay
Days added to the schedule times the overhead each day costs.
Change order price
Subtotal plus bond or insurance plus delay.
New contract sum
The original contract plus earlier change orders plus this one.

Worked example

  • Add six doors. Labor is 24 hours at $45.95, which is $1,102.80, with a 15% markup: $1,268.22. Materials are $2,400 with 15%: $2,760.00. The electrician's subcontract is $1,800 with 8%: $1,944.00. The subtotal is $5,972.22.
  • Bond and insurance at 1.5% add $89.58, and two extra days at $350 of overhead a day add $700.00. The change order price is $6,761.80.
  • On a $100,000 contract with $4,000 of earlier change orders, the new contract sum is $110,761.80.

What it assumes

  • This is a sample format. Check it fits your contract and local rules, including who must sign a change order and when.
  • Markup, bond and daily overhead come from your contract and your own costs. Type them in; nothing here is a standard rate.
  • Each line's markup is calculated on that line's cost only. If your contract stacks overhead and profit, put the combined rate in the markup box.
  • Nothing you type is saved or sent. Print or save the form as a PDF before you leave the page.
  • Amounts are rounded to cents line by line, so the lines add up to the total.

Review the text and adjust it to your own policies and contract before you send or sign it.

Questions

Who has to sign a change order before work starts?

Your contract says. Most name the owner or the owner's representative and require a written, signed change order before the extra work starts. Get the signature first, because a verbal go-ahead is hard to collect on later.

How do I save the form as a PDF?

Press Print or save as PDF, then choose Save as PDF as the printer in the print window. Only the form prints. Nothing is uploaded, so the file never passes through our servers.

Can I add overhead and profit to a change order?

That depends on your contract. Many contracts name a percentage for overhead and profit on changes, sometimes one rate for your own work and a lower one for subcontracts. Put the rate your contract gives in each markup box.

How does an approved change order show up on the next pay application?

It adds to the contract sum and appears as its own line in the schedule of values, which you bill like any other line. The pay application generator on this site takes approved change orders as lines.

Nagi Construction Management Suite

Nagi Construction Management Suite carries the markup on each change order as its own line, next to the cost, so the build-up stays visible.