Free tool
Change order calculator
- No sign-up, no email
- Nothing stored
In short
A change order price is the direct cost of the extra work, plus the markup your contract allows on each part, plus any bond or insurance, plus the overhead for days it adds to the schedule. Enter the costs and the markups and the calculator shows each step, the total and the new contract sum.
Price a change order
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Change order price
6,761.80
1,459.00 above direct cost (21.58% of the price).
- Labor: 1,102.80 + 15%
- 1,268.22
- Materials: 2,400.00 + 15%
- 2,760.00
- Subcontractors: 1,800.00 + 8%
- 1,944.00
- Subtotal with markup
- 5,972.22
- Bond or insurance
- 89.58
- Delay overhead
- 700.00
- Change order price
- 6,761.80
- Direct cost
- 5,302.80
- Markup earned
- 669.42
Bond and delay overhead recover costs, so they are not counted as markup.
How it is calculated
- Labor cost
- Hours times the burdened hourly rate (the wage plus its burden).
- Line price
- The line's cost plus its cost times its markup. Labor, materials, equipment and subcontractors each have their own markup.
- Subtotal
- The line prices added up.
- Bond or insurance
- The subtotal times the bond percentage.
- Delay
- Days added to the schedule times the overhead each day costs.
- Change order price
- Subtotal plus bond or insurance plus delay.
- New contract sum
- The original contract plus earlier change orders plus this one.
Worked example
- Add six doors. Labor is 24 hours at $45.95, which is $1,102.80, with a 15% markup: $1,268.22. Materials are $2,400 with 15%: $2,760.00. The electrician's subcontract is $1,800 with 8%: $1,944.00.
- The subtotal is $1,268.22 + $2,760.00 + $1,944.00 = $5,972.22.
- Bond and insurance at 1.5% of the subtotal is $89.58, which gives $6,061.80.
- Two extra days at $350 of overhead a day add $700.00. The change order price is $6,761.80, which is $1,459.00 above the $5,302.80 of direct cost.
What it assumes
- Markup, bond and daily overhead come from your contract and your own costs. Type them in; nothing here is a standard rate.
- Each line's markup is calculated on that line's cost only. Overhead and profit are not stacked on top of each other: if your contract stacks them, put the combined rate in the markup box.
- Bond and insurance are a percentage of the subtotal after markup. Delay overhead is added last and carries no markup.
- Every amount is in one currency. Amounts are rounded to cents line by line, so the lines add up to the total.
- The result is an estimate for planning. It is not a signed change order: your contract decides who must approve it and when.
These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.
Questions
How do I price a change order?
Add up the direct cost of the extra work: labor at the burdened rate, materials, equipment and subcontractors. Add the markup your contract allows to each part, then any bond or insurance and the overhead for added days. The calculator does these steps in order and shows each one.
Can I add overhead and profit to a change order?
That depends on your contract. Many contracts name a percentage for overhead and profit on changes, sometimes one rate for your own work and a lower one for subcontracts. Put the rate your contract gives in each markup box.
How do I account for lost time?
Enter the days the change adds to the schedule and the overhead each of those days costs you: site supervision, rented equipment, temporary facilities. The calculator adds days times that rate as its own line, after markup.
Who has to sign a change order before work starts?
Your contract says. Most name the owner or the owner's representative and require a written, signed change order before the extra work starts. Get the signature first, because a verbal go-ahead is hard to collect on later.
How does an approved change order show up on the next pay application?
It adds to the contract sum and appears as its own line in the schedule of values, which you bill like any other line. The progress billing calculator on this site takes approved change orders as lines.
Nagi Construction Management Suite
Nagi Construction Management Suite carries the markup on each change order as its own line, next to the cost, so the build-up stays visible.
Read more
Related free tools
- Change order form generator
Price a change order and print the form with the cost build-up, the new contract sum and signature lines.
- Construction purchase order with budget impact
Write a purchase order for a job and cost code, see what it does to the budget and match order, receipt and invoice.
- Markup vs margin calculator
Convert markup to margin, price a job for the margin you want, and find the markup your overhead needs.
- Labor burden rate calculator
Work out what one worker really costs per productive hour, with every cost line shown.