Free tool
Progress billing and retainage calculator
- No sign-up, no email
- Nothing stored
In short
A progress payment is the work completed to date, less retainage, less what earlier applications already certified. Enter each schedule of values line, your change orders and your retainage rate, and the calculator gives the nine summary lines of an application for payment, from the contract sum to date to the payment due and the balance to finish.
Application for payment
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Schedule of values
| Item | Description | Scheduled value | Done before | This period | Stored | % done | Remove |
|---|---|---|---|---|---|---|---|
| 52% |
Approved change orders
| Item | Description | Amount | Done before | This period | Stored | % done | Remove |
|---|---|---|---|---|---|---|---|
| 0% |
How it is calculated
- 1. Original contract sum
- The scheduled values of all original lines added up.
- 2. Net change by change orders
- Approved change orders added up. A deduction is a negative amount.
- 3. Contract sum to date
- Line 1 plus line 2.
- 4. Completed and stored to date
- For every line: work done before, plus work this period, plus materials stored. All lines added up.
- 5. Retainage
- The retainage rate times the work completed, plus the stored-materials rate times the stored materials. If your contract lowers the rate at a trigger, the lower rate applies to all work once the job reaches it. A cap limits the total.
- 6. Total earned less retainage
- Line 4 minus line 5.
- 7. Less previous certificates
- The total earned less retainage on your last application.
- 8. Current payment due
- Line 6 minus line 7.
- 9. Balance to finish, with retainage
- Line 3 minus line 6.
Worked example
- A contract of $250,000 with one approved change order of $10,000: line 3 is $260,000.
- Work done before is $80,000, this period $40,000 and stored materials $10,000, so line 4 is $130,000. The job is 50% complete.
- Retainage at 10% is $13,000, so line 6 is $117,000.
- The last application certified $72,000 ($80,000 less $8,000 retainage). Current payment due is $117,000 − $72,000 = $45,000, and the balance to finish is $260,000 − $117,000 = $143,000.
What it assumes
- Retainage rates, any drop in the rate and any cap come from your contract. Type them in; the calculator does not know what yours allows.
- A lower rate after a trigger is applied to all work to date, not only to new work. If your contract differs, leave the trigger blank and type the rate that applies.
- Stored materials use the same rate as work unless you type another.
- Previous certificates are what you typed. The calculator cannot see earlier applications.
- Only approved change orders belong in the table: pending ones do not change the contract sum.
- This is a calculator, not a form to submit. It follows the nine-line structure of a typical pay application and is not affiliated with the American Institute of Architects. Check what your owner requires, including any lien, notary or state wording.
- Amounts are worked out in whole cents. The result is an estimate for planning.
These results are estimates for planning. Check them against your own records and policies before you use them in a bid, a payroll run or an employee's balance.
Questions
What is retainage and who sets the percentage?
Retainage is a share of each progress payment that the owner holds back until the work is finished or accepted. Your contract sets the percentage, often 5% or 10%. Some states limit it, so enter the rate your contract and local rules give you.
Can retainage drop during the job?
Only if your contract says so. A common clause lowers the rate once the job is half done. Enter the trigger and the lower rate, and the calculator applies the lower rate to all work to date.
How do I bill stored materials?
Enter them in the Stored column of the line they belong to. They count toward the total completed and stored, and they carry retainage at the stored-materials rate. Most owners ask for proof such as invoices, so check what your contract requires.
Is this the official AIA form?
No. It follows the structure of a typical pay application, with nine summary lines on top of a schedule of values, but it is not the AIA document and is not affiliated with the AIA. Use it to check your numbers before you fill in the form your owner requires.
How do approved change orders change my application?
They add to the contract sum in line 2 and appear as their own lines in the continuation sheet, where you bill them like any other line. A change order that is still pending does not belong in the table until it is approved.
Nagi Construction Management Suite
Nagi Construction Management Suite builds applications for payment from the schedule of values, with retainage, stored materials and change orders, on your own PC.
Read more
Related free tools
- Construction invoice generator
Make a printable invoice for a lump sum, time and material or progress billing job, with retainage and a cap tracker.
- WIP and over/under billing calculator
Work out percent complete, earned revenue and over or under billing for every open job, with totals you can print.
- G702-style pay application generator
Make a printable application for payment with nine summary lines and a continuation sheet, in your browser.
- Subscription vs one-time license calculator
Compare a per-user subscription with a one-time license year by year, and see when the subscription catches up.