Free tool
Submittal log with submit-by dates
- No sign-up, no email
- Nothing stored
In short
A submittal log tracks the shop drawings, product data and samples you must send for approval. The date a submittal has to go out is the date the item is needed on site, minus its lead time, minus the time the reviewer needs. Enter those three and the log gives the submit-by date for every item, how many days are left and which are already late.
Your submittal log
Example numbers are filled in so you can see how it works. Replace them with yours. Nothing you type leaves this page.
Submittals
Type dates as year-month-day, like 2026-11-30. Submit by = needed on site minus the lead time minus the review time, in calendar days. Both times are yours: type what the supplier and the reviewer need.
| No. | Description | Spec section | Needed on site | Lead time (days) | Review time (days) | Submitted | Remove |
|---|---|---|---|---|---|---|---|
Enter the as-of date.
How it is calculated
- Submit by
- The needed-on-site date, minus the lead time, minus the review time. All three are calendar days.
- Days to go
- The submit-by date minus the as-of date. Negative means the date has passed.
- Late
- Not yet submitted, and the submit-by date is before the as-of date.
Worked example
- Curtain wall frames are needed on site on 1 March 2027. They take 21 days to make and the architect needs 14 days to review the shop drawings: 35 days in all.
- The submittal must go out by 25 January 2027. On 30 November 2026 that is 56 days away.
- A steel connection design needed on 20 December with 14 days of lead time and 10 days of review had to go out by 26 November: it is late on 30 November.
- If you expect a second round of review, add 10 days to the curtain wall's review time. The submit-by date then moves from 25 January to 15 January 2027.
What it assumes
- Lead time and review time are yours. The log does not know what your supplier or reviewer needs: type their real figures, and add time for resubmittals if you expect them.
- Times are calendar days, not working days.
- Dates are plain calendar dates you type as year-month-day.
- Nothing you type is saved or sent. Print or download the log before you leave the page. Sample format. Check it fits your contract and local rules.
Review the text and adjust it to your own policies and contract before you send or sign it.
Questions
What is a submittal?
Information sent to the designer for approval before something is made or installed: shop drawings, product data, samples. A submittal log lists them all with their status.
How do I work out when a submittal has to go out?
Start from the date the item must be on site, count back the time the supplier needs to make and deliver it, then count back the time the reviewer needs. That is the latest date to send it. The log does the sum for every row.
What if the first submittal is rejected?
Then the review time happens again. Add the time for a second round to the review days if you expect one, or the log will show a date that is too late.
Why use calendar days and not working days?
Supplier lead times are usually quoted in calendar days or weeks. If your reviewer counts working days, convert them to calendar days before you type them in.
What is the difference between a submittal and an RFI?
A submittal sends the design team something to approve, such as shop drawings, product data or samples. An RFI asks a question about the documents. Both need an answer by a date and both belong on a log. This page tracks the submittals.
How long does a submittal review take?
Specifications often set a number of days, and it differs from one project to the next. Type the number your specification or contract gives rather than a guess, and add days for a second round if the item is likely to be returned.
What does late mean on the log?
The submittal is not marked as submitted and its submit-by date is before the as-of date. It is late against the date the item is needed on site, which does not mean the job is behind. It means the date to send it has passed, so the item may arrive after it is needed.
Nagi Construction Management Suite
Nagi Construction Management Suite includes submittals, RFIs and transmittals, with a schedule that has dependencies and a critical path.
Read more
Related free tools
- RFI log
Log requests for information, see how long each has been open and which are past the response date, with cost and delay totals.
- Training and certification matrix
Track who has done which course and certificate, what is about to expire, and what is overdue, with a due list.
- Progress billing and retainage calculator
Work out an application for payment from your schedule of values, with change orders, retainage and stored materials.
- G702-style pay application generator
Make a printable application for payment with nine summary lines and a continuation sheet, in your browser.