Owner-architect-contractor meeting no. 12
16 Nov 2026, 09:00, Site office, Riverside Retail Unit
Chair: Tomas Reyes (Contractor) · Minutes: Mei Chen
Present: Tomas Reyes (Contractor), Owner's representative (Owner), Project architect (Architect), Mei Chen (Site safety)
Apologies: Structural engineer
1. Safety
No incidents. Housekeeping on the north side to be improved.
2. Schedule and three-week look-ahead
Steel frame is 12 days behind; recovery plan to be issued.
Decision: Contractor to issue a revised schedule.
3. RFIs and submittals
RFI 7 (door hardware) answered. Roof deck submittal is under review.
4. Change orders and pricing
Glazing change to be priced. Proposed change order 4 pending.
5. Payment application
Application 6 submitted on 13 November.
Actions
| Action | Owner | Due | Before next meeting | Done |
|---|---|---|---|---|
| Issue the revised schedule | Tomas Reyes | 23 Nov 2026 | Yes | No |
| Answer RFI 9 (stair detail) | Project architect | 27 Nov 2026 | No | |
| Price the glazing change | Tomas Reyes | 30 Nov 2026 | No |
3 open. Open by owner: Tomas Reyes 2, Project architect 1.
Next meeting: 23 Nov 2026